摘要 随着国际贸易海上贸易的发展,STX大连船厂为了拓展贸易,增大船厂生产能力,解决船舶停靠困难等问题,现拟建 STX大连船厂2#高桩码头。 由于大连港附近海流条件复杂,气候条件差,码头跨度长,桩位密集,抛填量大,工期紧张,特别是码头施工期季节跨度大,雨季、冬季施工困难,对合理安排施工有很大要求。 因此,需要根据天气气象状况变化及时安排相应的施工方法及施工工艺,以保证施工进度按计划完成。针对气候条件问题,安排专门人员收集气象站资料,提前进行施工安排。由于桩位密集,又需要进行护桩抛填,因此需要制定合理的打桩和抛填方案。针对冬雨季施工困难等问题,制定了相应的冬季、雨季施工措施。 施工组织设计的内容包括对工程量的把握,施工工艺的合理安排,施工所需人机材料等合理调度,合理的施工进度计划安排,施工组织方案的确定,施工质量与安全技术措施的制定等。62301
毕业论文关键词:施工组织设计;高桩码头;施工管理;施工工艺
Abstract With the development of international trade and maritime trade, STX Dalian shipyard in order to expand trade, increase the production capacity of the shipyard, to solve the problem of the difficulty of the berth of the ship, the proposed STX Dalian shipyard 2# high pile wharf. Due to the complexity of the Dalian port near the current conditions, poor weather conditions, long span wharf, pile bit dense, dumping a large quantity, time limit for a project is short, especially wharf construction season span, the rainy season, the winter construction difficulties and of reasonable arrangement of construction has great demand for. Therefore, it is needed to arrange the corresponding construction method and the construction technology according to the weather condition change timely, in order to guarantee the construction progress according to the plan. In view of the construction difficulties of winter and rainy season, the corresponding winter and rainy season construction measures are established. The content of construction organization design, including the grasp of quantities, the rational arrangement of the construction process, the required construction materials such as man-machine reasonable scheduling, reasonable construction schedule arrangement, determination of construction scheme, construction quality and safety technical measures of the formulation.
Keywords:Construction organization design,high pile wharf,construction management,construction technology
目录
第一章编制说明1
1.1编制说明..1
1.2编制原则.1
1.3设计的主要内容..1
第二章工程概况.2
2.1工程位置..2
2.2设计内容及建筑物等级..2
2.3自然条件..2
2.3.1风况..2
2.3.2雨雪状况2
2.3.3雾2
2.3.4水文状况3
2.3.5波浪状况3
2.3.6冰4
2.3.7地质状况4
第三章施工总体布置..6
3.1施工流程安排6
3.2施工总平面布置..6
第四章施工进度计划..8
4.1施工进度计划8
4.2施工计划横道图..8
第五章施工准备..10
4.1施工组织准备.10
4.2机械材料准备.10
4.3生产、生活条件准备.10
4.4文明生产条件准备..10
第六章分部分项工程主要工程量计算..11
6.1抛石护底11
6.2标准K分段及I分段PHC桩数量统计11
6.3桩帽..12
6.4承台、梁及面板..12
6.5标准K分段梁板钢筋用量13
6.6K9分段梁板钢筋用量..15
6.7标准锚固K分段梁板钢筋用量.17
6.8I分段梁板钢筋用量..19 STX大连船厂2#高桩码头施工组织设计+CAD图纸:http://www.youerw.com/gongcheng/lunwen_68474.html