摘要:本工程为江苏省金桥盐化集团有限责任公司台北盐场昌圩湖经济适用住房住宅小区8、9#楼土建安装工程施工,砖混结构,建筑面积8#楼4036.09平方米,9#楼2781.06平方米。施工组织设计包括总体设想、方案针对性及施工段划分、施工准备工作、劳动力、项目管理班子人员配备、素质及管理经验、施工机械设备配置、主要材料构件投入计划、各分部分项的施工方案及质量保证措施、雨季施工技术措施、安全生产保证措施、施工进度计划、文明施工与施工平面布置图、降低工程成本的措施。53407
毕业论文关键词:施工组织设计、计划进度、工程质量
Abstract: This project for jiangsu jinqiao salinization group co., LTD Taipei saltworks chang dongshanwei lake economic applicable housing residential area of civil engineering construction installation, 8, 9 # floor brick structure, construction area of 4036.09 square meters, 8 # floor 9 # floor 2781.06 square meters. Overall vision, including targeted construction organization design and construction period of pision, construction preparation work, labor, project management team personnel, quality and management experience, construction machinery and equipment configuration, main material component of investment plan, the partial construction scheme and quality assurance measures, the rainy season construction technical measures, production safety guarantee measures, construction progress plan, civilization construction and construction layout, the measures of reducing the project cost
Keywords: construction organization plan,the quality of the project,construction plan
目 录
1 设计选题说明 4
1.1 选题原因说明 4
1.2 数据资料的获得 4
1.3 设计的难度 4
1.4 设计实现的可能性 4
2 设计依据 4
2.1 理论与方法 4
2.2 规范 4
2.3 参考文献的选用 5
3 设计的技术路线 5
3.1 主要方法 6
3.2 其他方法 7
4 设计的价值 8
4.1 对专业学习作用 8
4.2 对今后工作作用 9
结论 10
参考文献 11
致谢 12
1 设计选题说明
1.1 选题原因说明
本人在实习过程中通过学习、实践,了解了施工组织设计对于整个工程的指导性意义,通过施工设计能把设计与施工,理论与实践相结合,寻找共同点和差异。本课题将详细阐述淮安市昌圩湖经济适用房住宅小区8、9#楼施工组织设计对具体工程的安排和指导。
1.2 数据资料的获得
本工程为江苏省金桥盐化集团有限责任公司台北盐场昌圩湖经济适用住房住宅小区8、9#楼土建安装工程施工,砖混结构,建筑面积8#楼4036.09平方米,9#楼2781.06平方米。
在施工单位实习,使我能够获得相关资料。渠道包括寻找工程图纸,投标标书,也有像专业人员咨询。为了完成本次毕业设计的施工组织设计,我咨询了编制人员以及老师,并且实地观测现场施工。除此之外,还要通过网络查阅相关资料,了解一些没有接触过的工序,结合书本和老师课堂上的讲述弄清其作用和意义。