摘要:本次毕业设计做的是镇江新城市花园四期1-6#楼工程脚手架施工方案设计。本工程位于镇江市润州区港朱方路东、沪宁铁路线以北。主楼为框架剪力墙结构,抗震设防烈度为7度,抗震设防类别为丙类,结构安全等级为二级,抗震等级为二级,地下室部分建筑面积为22838㎡。基础为灌注桩、基础梁、承台及筏板构成箱式基础。各楼号由1-6#楼住宅、公寓,1-4#地下车库、5-6#地下车库组成。施工方案设计可具体分为编制依据说明,工程概况及特点,施工部署,施工总平面布置,施工总进度计划及工期保证措施,施工人员配备,主要项工程施工方法和质量要求,工程质量保证措施,安全文明。53431
毕业论文关键词:施工方案设计,进度计划,工程质量
Abstract: This graduation design is design scaffold construction scheme of Zhenjiang new city garden four building engineering 1-6#. This project is located to the north of Runzhou District of Zhenjiang city Hong Zhu Fang Road East, Shanghai Nanjing railway line. The main building is a frame shear wall structure, the seismic intensity of 7 degrees, the seismic fortification category C, structural safety grade two level, seismic grade two, the basement of a building area of 22838 square meters. Box type foundation for pile foundation, foundation beam, pile cap and raft. The building consists of 1-6#, 1-4# apartment building, underground garage, underground garage composition 5-6#. Construction scheme design can be pided into compilation basis, project general situation and characteristics, construction deployment, construction general layout, construction schedule and construction assurance measures, construction personnel, the main construction methods and quality requirements, construction quality assurance measures, safety and civilized.
Keywords:Design and construction plan, schedule, engineering quality
目录
1 设计选题说明 4
1.1 选题原因说明 4
1.2 设计项目概况 4
1.3 设计目的和要求 6
1.4 数据资料的获得 6
1.5 设计的难度 7
1.6 设计实现的可能性 7
2 设计依据 7
2.1 理论与方法 7
2.2 规范 7
2.3 参考文献的选用 8
3 设计的技术路线 8
3.1 主要方法 8
3.2 脚手搭设要求 8
3.3 搭设流程 10
4 设计的价值 10
4.1 对专业学习的作用 10
4.2 对社会工作的作用 10
结 论 11
参考文献 12
致 谢 13
1 设计选题说明
1.1 选题原因说明
本人因为大三暑假就在常州一建第三项目部镇江益华广场一期工地实习,大四又到三部负责的镇江新城市花园四期1-6#楼工程工地实习,实习期间对脚手架的施工方案设计这个课题很有研究的兴趣,并且因为长时间在工地实习,能接触到丰富的相关资料、数据等,所以选择这个研究课题进行毕业设计。