摘 要:本混凝土工程施工方案设计以拟南京四季花苑小区4号楼混凝土工程施工方案设计为例,对项目的主要分部分项工程施工方案进行了详细设计。本次设计是在认真研究图纸和现场考察的基础之上编制而成,在编制过程中运用了一些理论知识,如进度控制的理论。为了分析进度计划,还采用了横道图。编制了完整的混凝土施工方案设计,来确保进度、质量和成本这个三个目标的实现。54166
毕业论文关 键 词:混凝土,施工方案设计,进度控制,横道图
Abstract: The concrete construction design to the proposed Four Seasons Garden District, Building 4, Nanjing concrete construction organization design as example, the main points of the project on the part of the project construction program has been designed in detail.This design is the basis of a careful study of the above drawings and site visits are compiled,Use of some theoretical knowledge in the preparation process, such as the progress of control theory.To analyze the progress of the plan, also adopted the Gantt Chart.Preparation of a complete concrete construction design, to ensure the progress, quality and cost of this three objectives.
Keywords:Concrete construction design, Progress Control, Gantt Chart
目录
1 设计选题说明 1
2 设计依据 1
2.1 主要内容 1
2.2 规范 1
2.3 参考文献的选用 2
3 设计的技术路线 2
4 设计的价值 2
4.1 对专业学习的作用 2
4.2 对社会工作的作用 2
结论 3
参考文献 4
致 谢 5
1 设计选题说明
混凝土工程施工方案设计是一种经济技术文件,它是为了正确并且科学地指导混凝土施工准备和施工全过程而编制的一种文件。
这次毕业设计是以南京四季花苑小区4号楼混凝土工程施工方案设计为例,来编写整个混凝土施工方案设计,这不但是对我四年学习的专业知识的一种综合应用,而且对我个人来说也是一种文化的提升和深化。
在整个编制过程中,我针对设计任务,对相关专业知识进行了复习与巩固,同时查阅了相应的规范、资料,了解了施工方案设计文件包含的内容,通过所学的基本理论、专业知识和基本技能,进行混凝土施工组织设计的编制。
2 设计依据
2.1 主要内容
1.混凝土浇筑方案选择: 本工程混凝土采用现场搅拌。混凝土场内运输采用混凝土固定输送泵配合布料杆使用。
2.施工进度计划安排:
开工日起为2010年11月27日,计划竣工于2012年11月22日,总工期612日历天。
基础结构工程期限:2011年3月1日——2012年5月6日,工期228日历天。
主体结构工程期限:2012年5月1日——2012年9月6日,工期190日历天。
3.劳动力计划安排:泵送混凝土施工中,配备混凝土输送泵司机2人,搅拌机司机4人,指挥信号联络4人,混凝土入泵车前检测坍落度1人,混凝土布料杆操作人4人,机修电工2人,混凝土振捣工10人,整个生产线需25至30人。
2.2 规范源'自:优尔`!论~文'网www.youerw.com
本次混凝土施工方案设计所依据的规范主要为以下几个。