摘要:本毕业设计是泰安宝龙城市广场6#施工组织设计与加固改造。泰安宝龙城市广场6#楼为三层框架结构工程屋顶有十一户空中别墅。施工组织设计可分为编制依据及说明,工程概况及工程特点,施工部署,施工总平面布置,施工总进度计划及工期保证措施,施工人员配备,主要分部分项工程施工方法和质量要求,工程质量保证措施,安全文明。54137
毕业论文关键词:施工组织设计,加固改造,框架结构
Abstract: This graduation design is strengthening and reconstruction of Tai'an Powerlong City Plaza 6# construction organization design. Building 6# Powerlong City Plaza Tai'an is three layer frame structure with eleven households villa roof. The construction organization design can be pided into the basis and explanation, the engineering situation and the engineering characteristics, construction deployment, construction general layout, construction schedule and construction assurance measures, construction personnel, the main sub segment of the construction methods and quality requirements, construction quality assurance measures, safety and civilized.
keywords: Strengthening the construction organization design, framework,structure
目录
1 设计选题说明 4
1.1 选题原因说明 4
1.2 设计项目概况 4
1.3 设计目的和意义 4
1.4 数据资料的获得 5
1.5 设计的难度 5
1.6 设计实现的可能性 5
2 设计依据 5
2.1 编制依据 5
2.2 编制说明 5
2.3 参考文献的选用 6
3 设计的技术路线 6
4 设计成果的分析 6
5 设计的价值 7
5.1 对专业学习的作用 7
5.2 对社会工作的作用 7
结论 8
参考文献 9
致谢 10
1 设计选题说明
1.1 选题原因说明
本人对施工组织设计这个课题非常感兴趣,并且在房地产开发公司实习,能接触到大量的资料、数据等,所以选择这个课题进行毕业设计。
1.2 设计项目概况
工程名称:泰安宝龙城市广场6#加固工程
建设单位: 泰安宝龙实业发展有限公司
设计单位:南京凯盛建筑设计公司
泰安宝龙城市广场6#楼为三层框架结构工程屋顶有十一户空中别墅。屋顶种植土厚度原设计负荷已超过,屋面板裂缝严重,裂缝呈龟裂形,而且裂缝有严重的渗水现象。渗流问题已影响到了正常的1-2楼业务,屋面种植大量大型乔木都未做阻根处理。重做的可能性几乎没有。
其基本思想是:1、降低种植土壤贮水(导出种植土内蓄水),每框架区域内取一排水点将水导出;2、裂缝缝隙内高压灌注水溶性聚氨酯化学灌浆材料以取得密闭裂缝阻止渗水及防护钢筋继续锈蚀的作用;3、屋面板下部跨中区域增设钢梁用以减小板跨从而提高单元内混凝土板的承载力;4、对部分承载力不足的梁采取相应加固措施;5、增设钢结构平台用以收集渗水并组织排水;6、对堵塞的原天沟、虹吸等做疏通处理;7、屋面乔木采取阻根处理措施;8、对3F伸缩缝重做处理,以防止日后此处漏水至楼下。