摘要随着电网结构日益复杂,电网合理的分区分层已经成了电力行业的重要研究内容。针对已经进行分区运行的电网,当出现不同电压等级的设备如主变以及线路过载的情况,本文给出了对电网过载负荷进行转供的处理方案。对应具体情况,可以采用负荷转供、电磁环网解合环等以线路投切为核心的动态分区技术来减缓或解决设备过载问题。本文进一步选取了电网的几种重要指标建立了分区电网评价指标体系,对不同的动态分区方案进行综合评价,从而得到了适用的具体方案。通过具体的算例表明,该动态分区方案可以解决电网设备过载问题,保证电网安全稳定运行。84371
毕业论文关键词 电网分区分层 电磁环网解合环 负荷转供 动态分区 综合评价体系
毕业设计说明书外文摘要
Title Auxiliary decision making of equipment overload based on dynamic partitioning technology
Abstract With the increasing complexity of power grid structure, the reasonable partition layer of power grid has become an important research content in the power industry。 In view of the power grid which has already been carried out in the area, when there are different voltage levels of equipment such as the main transformer and the overload of the line, this paper presents the processing scheme of the overload load。 Corresponding to the specific circumstances, using the load transfer, the electromagnetic loop network solutions and so on line as the core of the dynamic partitioning technology to slow down or solve the problem of equipment overload。 In this paper, several important indicators of the power grid are selected to establish the evaluation index system of the regional power grid, and the comprehensive evaluation of different dynamic zoning plan is carried out。 Through the concrete example, it shows that the dynamic partition scheme can solve the overload problem of power system equipment, and ensure the safe and stable operation of power network。
Keywords load transfer the dynamic partitioning technique the dynamic zoning plan
目 次
1 绪论 1
1。1 课题背景与意义 1
1。2 课题研究现状 2
1。3论文的主要研究工作 5
2 动态分区技术原理及其简单算例 6
2。1 传统电网分区 6
2。2 现阶段的动态分区技术 7
3 针对设备过载的动态分区方案自动搜索算法 15
3。1引言 15
3。2启动判据 15
3。3可选方案空间 16
3。4 效果评价指标 16
3。5计算流程 17
4 动态分区策略的量化评价指标体系 19
4。1 引言 19
4。2 电网评价体系的基本框架 19
4。3 常规电网评价指标评价体系的建立 19
4。4 动态分区方案的综合评价法 22
5 算例仿真 24
5。1 选取解决过载的待校核方案 24