βox = 0.84/(0.232+0.2) = 1.943
Y 方向上自柱边到最近桩边的水平距离:
aoy = 750 - bc / 2 - bp / 2 = 750-700/2-433/2 = 183mm
λoy = aoy / ho = 183/(900-110) = 0.232
Y 方向上冲切系数 βoy = 0.84 / (λoy + 0.2) (基础规范 8.5.17-4)
βoy = 0.84/(0.232+0.2) = 1.943
2 * [βox * (bc + aoy) + βoy * (hc + aox)] * βhp * ft * ho
= 2*[1.943*(700+183)+1.943*(700+183)]*0.992*1.43*790
= 7708912N ≥ Fl = 5854140N,满足要求。
(2)、角桩对承台的冲切验算:
扣除承台和其上填土自重后的角桩桩顶相应于荷载效应基本组合时的竖向力设计值:
Nl = Nmax = 1463535N
承台受角桩冲切的承载力按下列公式计算:
Nl ≤ [β1x * (c2 + a1y / 2) + β1y * (c1 + a1x / 2)] * βhp * ft * ho
(基础规范 8.5.17-5)
X 方向上自桩内边缘到最近柱边的水平距离:
a1x = 750 - hc / 2 - bp / 2 = 750-700/2-433/2 = 183mm
λ1x = a1x / ho = 183/(900-110) = 0.232
X 方向上角桩冲切系数 β1x = 0.56 / (λ1x + 0.2) (基础规范 8.5.17-6)
β1x = 0.56/(0.232+0.2) = 1.295
Y 方向上自桩内边缘到最近柱边的水平距离:
a1y = 750 - bc / 2 - bp / 2 = 750-700/2-433/2 = 183mm
λ1y = a1y / ho = 183/(900-110) = 0.232
Y 方向上角桩冲切系数 β1y = 0.56 / (λ1y + 0.2) (基础规范 8.5.17-7)
β1y = 0.56/(0.232+0.2) = 1.295
桩内边缘到承台外边缘的水平距离:
c1 = c2 = Sc + bp / 2 = 500+433/2 = 717mm
[β1x * (c2 + a1y / 2) + β1y * (c1 + a1x / 2)] * βhp * ft * ho
= [1.295*(717+183/2)+1.295*(717+183/2)]*0.992*1.43*790
= 2350801N ≥ Nl = 1463535N,满足要求。
3、承台斜截面受剪承载力计算:
(1)、X方向斜截面受剪承载力计算:
扣除承台及其上填土自重后 X 方向斜截面的最大剪力设计值:
Vx = Max{N1 + N2, N3 + N4} = 2927070N
承台斜截面受剪承载力按下列公式计算:
Vx ≤ βhs * βy * ft * bxo * ho (基础规范 8.5.18-1)
X 方向上自桩内边缘到最近柱边的水平距离:
ay = 750 - bc / 2 - bp / 2 = 750-700/2-433/2 = 183mm
λy = ay / ho = 183/(900-110) = 0.232
- 上一篇:建设工程项目施工进度管理研究
- 下一篇:上海综合大楼的空调设计说明书+CAD图纸
-
-
-
-
-
-
-
上市公司股权结构对经营绩效的影响研究
C++最短路径算法研究和程序设计
巴金《激流三部曲》高觉新的悲剧命运
高警觉工作人群的元情绪...
现代简约美式风格在室内家装中的运用
NFC协议物理层的软件实现+文献综述
浅析中国古代宗法制度
江苏省某高中学生体质现状的调查研究
中国传统元素在游戏角色...
g-C3N4光催化剂的制备和光催化性能研究