    摘 要:在我国社会主义建设工作的要求下,我国的建筑产业也得到了极大的发展空间。且由于人口数量的剧增,国人对于建筑产业的刚性需求也愈来愈大了,但这也给建筑企业的发展带来了空前的压力。建设工程项目一般投资大、周期长,为保证建设工程项目顺利实施,进度控制需全面、客观、有效并具有前瞻性。这就显得建筑企业对于工程施工进度的控制工作尤为重要了,进度管理工作是贯通着工程全过程管理的一项重要工作,其对施工的各项工作都有着很大的影响。本文将就工程管理中的施工进度管理进行分析:
        首先,就建设工程项目进度管理作简要的概述,讲述进度管理的方法,分析进度管理人为、环境、资源、施工方法的影响因素。提出一系列保证措施,包括施工管理组织的保证措施、施工技术的保证措施、施工各项物资的保证措施、施工设备管理的保证措施、施工劳动力保证措施。
    接着,根据进度计划的编制依据和编制工具,从适用的、可操作性强的角度,就怎样编制一份建设工程施工进度计划作了具体的阐述,包括工作分解结构图、网络计划图、时间参数的计算、关键线路的确定等等。同时,又针对可能出现的偏差提出解决方案。
    最后,运用上述提到的研究方法,结合天成综合楼建设工程项目,提出施工进度计划与控制的作业程序是一个不断上升的过程,着重对进度计划实施过程中应注意的问题、调整处理等方面进行了论述,以实现工程项目进度总目标。4414
        
    关键词:建设工程;施工进度;进度管理

    Research on schedule management of construction project

    Abstract: In the work of our country's socialist construction requirements, China's construction industry has also been a great development space. And because the population explosion, the rigid demand of people in the building industry is more and more big, but also to the development of construction enterprises has brought unprecedented pressure. Construction project general large investment, long cycle, in order to ensure the smooth implementation of construction projects, schedule control need comprehensive, objective, effective and forward-looking. This would be very important that the construction enterprises should contorl the work progress, schedule management work is an important work through the whole process of project management, the work of the construction has a great influence. This paper will analyze the construction schedule management in project management:

    First of all, on the construction project management is briefly outlined, about progress management method, analysis of the factors influencing the schedule management, environment, human resources, construction method. Put forward a series of measures, including measures to ensure the construction technology, construction organization, construction measures to guarantee the material guarantee measures, construction equipment management and assurance measures, construction labor assurance measures.

    Then, according to the basis schedule plan and development tool, from the application angle, can be operable, on how to prepare a construction project construction schedule were discussed, including the work breakdown structure, network planning chart, time parameter calculation, the key line determination etc.. At the same time, and proposed the solutions to the possible bias.

    Finally, by using the method of the above mentioned, combined with Tiancheng Building construction projects, the construction schedule and control procedures is a rising process, discusses emphatically the implementation should pay attention on the schedule problems, adjust the treatment, in order to achieve the project goals.

    KeyWords:construction engineering;construction schedule;schedule management
  1. 上一篇:五层现浇钢筋混凝土框架结构商业中心建筑与结构设计和CAD图纸
  2. 下一篇:五层教学楼框剪结构建筑设计和结构设计计算书和CAD图纸
  1. ANSYS大跨度预应力张弦梁结构施工过程模拟

  2. 钢筋混凝土现浇框架结构...

  3. 高层建筑施工安全管理研究

  4. 镇江海绵城市建设的居住区景观设计

  5. 扬州港港区6万吨级件杂货...

  6. 空气化工产品公司榆林办...

  7. 基于网络计划技术对建设工程项目的优化

  8. 江苏省某高中学生体质现状的调查研究

  9. 高警觉工作人群的元情绪...

  10. 现代简约美式风格在室内家装中的运用

  11. 中国传统元素在游戏角色...

  12. g-C3N4光催化剂的制备和光催化性能研究

  13. 浅析中国古代宗法制度

  14. C++最短路径算法研究和程序设计

  15. NFC协议物理层的软件实现+文献综述

  16. 上市公司股权结构对经营绩效的影响研究

  17. 巴金《激流三部曲》高觉新的悲剧命运

  

About

优尔论文网手机版...

主页:http://www.youerw.com

关闭返回