摘要连云港徐圩港区预制厂构件出运码头施工组织设计在编制过程中认真参考 并研究了各项水文资料和施工现场条件,本着强化质量管理、合理安排工期、降 低资源消耗的原则,尽可能的优化了施工方案。充分利用公司已有的和国内先进 的生产设备和船机设备,投入足够满足本工程施工强度要求的施工机械设备,组 织进行机械化和专业化施工,以确保本工程能够在工期内保质保量完成。 78250

毕业论文关键词:沉箱码头;施工组织设计;施工工艺。

Abstract The construction organization design of Lianyungang XuWei port precast component factory shipment wharf during the process of compiling is designed to give serious consideration according to the hydrological data and construction site

conditions,   with   the  purpose  of  strengthening  quality  management , make  the

arrangement of time reasonable , reducing the consumption of resources, as far as possible to optimize the construction scheme。 Making full use of the  existing company and domestic advanced production equipment and ship machine equipment, investing enough to meet the requirements of the strength of the construction of the project of construction machinery and equipment machinery and professional construction organization, to ensure that the works can within the time limit for a project to complete the quality and quantity。

Keywords: caisson quay;construction organization design;construction technology。

目录

第一章  绪论 1

1。1 施工组织设计的意义 1

1。2 编制说明 1

1。3 编制依据 1

1。4 编制原则 2

第二章  工程概况 3

2。1 水位资料 3

2。2 海流资料 3

2。3 风 4

2。4 气温 6

2。5 降水 6

2。6 工程地质条件 7

第三章  施工总平面布置 9

3。1 布置原则 9

3。2 施工总平面布置 9

3。3 施工总平面布置图 10

第四章  分部分项工程的主要工程量 12

4。1 工程量汇总 12

4。2 工期安排 17

4。3 船机、测量器具使用统计 18

4。4 施工横道图 20

第五章  测量工程 21

5。1 控制点的确认 21

5。2 平面控制系统 21

5。3 高程控制系统 21

5。4 施工过程中的测量控制 21

5。5 测量点平面布置示意图 22

5。6 测量仪器汇总 22

第六章  基槽挖泥 23

6。1 总体配置 23

6。2 施工布置 24

6。3 分项工程简略图

上一篇:滁州港重力式码头设计+图纸
下一篇:射阳港3000吨级散货码头设计及施工组织设计+图纸

连云港新浦区某旅游宾馆建筑及结构设计

连云港市某小区住宅楼建筑及结构设计

连云港港徐圩港区高桩码头工程设计+图纸

和尚岛港区2万吨级码头主体工程设计+图纸

扬州港港区6万吨级件杂货...

镇江市大港港区5万吨级散...

南通港狼山港区三期2#集装...

互联网教育”变革路径研究进展【7972字】

网络语言“XX体”研究

LiMn1-xFexPO4正极材料合成及充放电性能研究

安康汉江网讯

张洁小说《无字》中的女性意识

我国风险投资的发展现状问题及对策分析

新課改下小學语文洧效阅...

ASP.net+sqlserver企业设备管理系统设计与开发

麦秸秆还田和沼液灌溉对...

老年2型糖尿病患者运动疗...